Warehouse Lighting Update Week 2 and Week 3.
Week 2 – Reinstalling lighting bus bar at high level. More racking completed.
Week 3 – The first light being prepared to be installed by A Coole Electrical Team.
Works still continuing in this warehouse for another 4 weeks, A Coole Electricians will be fitting over 150 Lights in total.